All five members of a project team

1. All five members of a project team add 15% to their individual serial activities as a safety margin and submit their time estimates to the project manager. The manager adds the activity length estimates together and adds 10% for his personal safety margin. Then, anticipating a cut by top management, adds another 10% to his final project estimate. Much to his surprise, top management cuts 30% off his time estimate. How much of a cushion is now built into the project?

 

a 13%

b. 7%

c. 5%

d. -3%

 

2. All five members of a project team add 20% to their individual serial activities as a safety margin and submit their time estimates to the project manager. The manager adds the activity length estimates together and adds 20% for his personal safety margin. Then, anticipating a cut by top management, adds another 20% to his final project estimate. The executive level of the organization just completed a retreat where they read The One Minute Manager, Who Moved My Cheese and Critical Chain. They return from their retreat both energized and much wiser in the ways of project management. They know that everyone has been routinely adding 20% and want to scale the project back to an unpadded estimate. How much should they cut?

 

a. 42%

b. 60%

c. 33%

d. 27%

 

3. The student syndrome of wasting extra safety time can be described as ______________.

 

a. lack of motivation

b. procrastination

c. failure to communicate

d. lack of comprehension

 

4. Which of the following statements about CCPM activity networks is correct?

 

a. Project workers are more likely to meet a deadline for their activity than miss it.

b. There are no milestones in the CCPM activity network.

c. Project workers are more likely to miss a deadline for their activity than meet it.

d. There is no project delivery deadline in the CCPM activity network.

 

5. Subcontractor deliveries are difficult to schedule with the critical chain project methodology because ____________.

 

a. the project manager cannot force subcontractors to use this project management approach

b. the feeder buffers for a subcontractor are as much as 50% shorter than for an employee or internal team

c. subcontractors routinely operate according to calendar delivery dates

d. the corporate culture of “no blame” does not naturally extend to subcontractors

 

6. The buffers supplied to noncritical paths in critical chain project management are called _____________ buffers.

 

a. slack

b. drum

c. rope

d. feeder

 

7. The amounts of individual resources that a schedule requires during a specific time period is referred to as the resource’s ______________.

 

a. loading

b. capacity

c. constraint

d. drag

 

8. A resource loading form is also known as a(n) ______________.

 

a. load schedule

b. resource usage calendar

c. activity resource schedule

d. network resource profile

 

9. A resource loading chart displays the amount of ______________.

 

a. time needed as a function of resource limits

b. resources required as a function of time

c. time needed as a function of money

d. resources needed as a function of money

 

10. Splitting activities refers to _____________.

 

a. assigning the work to two or more workers

b. assigning the work to two or more days

c. starting an activity, interrupting it to use a resource elsewhere and then returning to work on the activity

d. breaking each noncritical activity into two or more components and subdividing the resources they use by a similar divisor

 

11. The Minimum Late Finish Time rule stipulates that the _____________.

 

a. earliest late finishers are scheduled last

b. latest early finishers are scheduled first

c. earliest late finishers are scheduled first

d. latest late finishers are scheduled first

 

12. Mathematical programming is sometimes used to generate optimal solutions to resource constrained problems in a multi-project setting but suffers from _____________.

 

a. an inability to model project and activity due dates

b. resource substitution

c. resource constraints

d. problem complexity

 

13. In earned value management, schedule variance is defined as the difference between the _____________.

 

a. earned value and the actual cost

b. earned value and the planned value

c. actual cost and the planned value

d. cost and schedule performance indices multiplied by the budgeted cost at completion

 

14. The budget variance is calculated as _____________.

 

a. earned value minus planned value

b. planned value minus actual cost

c. earned value minus actual cost

d. cost minus planned value

 

15. In earned value management analysis, the cumulative amount of the budget becomes the _____________.

 

a. planned value

b. scheduled value

c. cost basis

d. cost driver

 

16. The project baseline is established by combining data from the _____________.

 

a. work breakdown structure and the project budget

b. time-phased project budget and the PERT chart

c. S-curve and the project budget

d. time-phased project budget and the work breakdown structure

 

17. Take the factors considered by earned value analysis and subtract those considered by project S-curves. The factor(s) you have remaining are _____________.

 

a. performance and cost

b. cost and schedule

c. time

d. performance

 

18. Knowing the correct steps to take once problems develop is a function of a team’s ___________ ability.

 

a. communication

b. client acceptance

c. troubleshooting

d. technical task

 

19. Earned value management is also known as _____________.

 

a. the golden triangle method (GTM)

b. the achieved value method (AVM)

c. the program evaluation and review method (PERM)

d. earned value analysis (EVA)

 

20. All projects are unique _____________.

 

a. therefore all project management circumstances are equally unique

b. so knowledge cannot be transferred

c. but they may have several common points

d. so knowledge should not be transferred to avoid bias in future projects

 

21. Lessons learned analysis is best described as a(n) ______________ process.

 

a. bookkeeping

b. personnel reassignment

c. pressure relief

d. organizational learning 

 

22. Which of these is not a consequence of a natural process for project closeout?

 

a. Team members suffer a natural let-down and are de-motivated to participate in future projects.

b. Managers can create a database of lessons learned analyses.

c. Closeout can serve as an important source of information for team members.

d. Structure for a systematic and complete project shut-down arises.

 

23. Which of these statements about early termination decisions is best?

 

a. The decision to pull the plug is usually clear-cut.

b. A project’s viability is usually a purely internal issue.

c. Projects that can fulfill a useful purpose in the marketplace are not killed.

d. External reasons, such as a change in the organizations environment, are often the reasons for project termination.

 

24. A mainframe computer company decided to enter the personal computer market with its Floridian Project, but subsequently decided to leave the market to focus on the mainframe business. The decision rule that they probably applied was to get out when ____________.

 

a. the project no longer meets strategic fit criteria

b. deadlines continue to be missed

c. project personnel turn over too rapidly

d. technology evolves beyond the project’s scope

 

25. The rapid evolution of technology and the need to freeze a project’s scope can combine to render a project ____________.

 

a. too costly to complete

b. obsolete before it can be finished

c. a poor fit with current company strategy

d. so complex that it will take too long to complete

 

Order a unique copy of this paper
(550 words)

Approximate price: $22

Basic features
  • Free title page and bibliography
  • Unlimited revisions
  • Plagiarism-free guarantee
  • Money-back guarantee
  • 24/7 support
On-demand options
  • Writer’s samples
  • Part-by-part delivery
  • Overnight delivery
  • Copies of used sources
  • Expert Proofreading
Paper format
  • 275 words per page
  • 12 pt Arial/Times New Roman
  • Double line spacing
  • Any citation style (APA, MLA, Chicago/Turabian, Harvard)

Our guarantees

We value our customers and so we ensure that what we do is 100% original..
With us you are guaranteed of quality work done by our qualified experts.Your information and everything that you do with us is kept completely confidential.

Money-back guarantee

You have to be 100% sure of the quality of your product to give a money-back guarantee. This describes us perfectly. Make sure that this guarantee is totally transparent.

Read more

Zero-plagiarism guarantee

The Product ordered is guaranteed to be original. Orders are checked by the most advanced anti-plagiarism software in the market to assure that the Product is 100% original. The Company has a zero tolerance policy for plagiarism.

Read more

Free-revision policy

The Free Revision policy is a courtesy service that the Company provides to help ensure Customer’s total satisfaction with the completed Order. To receive free revision the Company requires that the Customer provide the request within fourteen (14) days from the first completion date and within a period of thirty (30) days for dissertations.

Read more

Privacy policy

The Company is committed to protect the privacy of the Customer and it will never resell or share any of Customer’s personal information, including credit card data, with any third party. All the online transactions are processed through the secure and reliable online payment systems.

Read more

Fair-cooperation guarantee

By placing an order with us, you agree to the service we provide. We will endear to do all that it takes to deliver a comprehensive paper as per your requirements. We also count on your cooperation to ensure that we deliver on this mandate.

Read more

Calculate the price of your order

550 words
We'll send you the first draft for approval by September 11, 2018 at 10:52 AM
Total price:
$26
The price is based on these factors:
Academic level
Number of pages
Urgency